|
St.
Antoninus Building & Grounds Commission
Date:
March,
2008
No meeting , notes on project updates:
School roof:
The school roof
copper dormers have been replaced.
The copula on the
school was inspected and shown to be in decent shape. There is need
for some maintenance/ painting. It covers 2 roof vents, so it is a
needed.
School Chiller:
The school ice bank
system will be bypassed starting this spring (due to several issues
with that system). We are waiting on a final schedule. This
involves some piping and programming changes.
We are getting
quotes on in-room air conditioners for the 2 computer room (vs using
the ones in the windows)
Health
inspection
was completed; this involved a more thorough review based on the new
Jarod’s Law. A remediation plan will be filed within 60 days.
There were no major items cited. General categories: Cabinets and
tables that need to be secured due to possible tip hazard, MSDS
sheets needed for items in classrooms, Locker room floors need to be
cleaned, Science & Art room specifics.
The pew
refinishing is schedule from May 30 (center sections
removed) to be returned by June 28th.
Undercroft
Plans:
The group is
completing bids on the flooring, ceiling and electric. The plan is
to start work on the new storage area in May.
Cleanup Day will be Saturday April 26th.
Some pre-work has
already been done- the dead shrubs were removed.
Elder students did
some community service hours to pickup around the grounds.
Some trees were
planted by Greg Lester.
Summer
Painting:
In School: We will
utilize David Endres as a supervisor of the paint projects this
summer along with summer high school help. The projects are:
old school hallway and door frames. There are also some areas at
church and the rectory that require painting.
Facility Exterior:
Peggy is getting bids on painting needed around the campus exterior.
New items:
The 1st
floor classrooms (specifically rm 19) have a raised threshold at the
doorway that is causing a trip hazard.
There is a
project to renovate the scout room. It is being done as an Eagle
Scout project. Father has approved this project and is allowing
solicitation of funds as this is part of the St. Antoninus facility.
Next meeting planned Monday
April 14th 7:30
The
Undercroft planning group will meet prior at 6:30pm in Undercroft.
RETURN TO TOP
St.
Antoninus Building & Grounds Commission
Date: Feb. 11,
2008
Attendees: Greg
Langenbrunner, Randy Palicki, Dave Endres, Mark Cappel, Bill
McIntyre, Mary Hirlinger, Mike Egner, Fr. Armstrong, Peggy James
Meeting
notes/updates:
The school roof
copper dormers have been replaced.
The copula on the
school was inspected and shown to be in good shape. There is need
for some minor maintenance. It covers 2 roof vents, so it is a
needed.
The school ice bank
system will be bypassed starting this spring (due to several issues
with that system). We are waiting on a final schedule. This
involves some piping and programming changes.
New items/
discussion:
We are getting
quotes on in-room air conditioners for the 2 computer room (vs using
the ones in the windows)
A light in the
lower parking lot is out and needs to be replaced- this is one that
Duke maintains, they will be contacted.
Jarod’s Law is new
legislation that requires a lot more detailed inspection by the
Health Department.
(This law is
generally a school safety item; named after a child that was killed
from a folded lunch room table)
We will have our
inspection later this month. Key areas of focus will be: MSDS
sheets, Bleacher inspection, Lunch room inspection and Roof
inspection.
The group was asked
to approve proceeding with the pew refinishing project. The center
sets of pews in church are in need of refinishing. The “pie”
sections were done 2 years ago. The group agreed. The schedule
will be setup to minimize disruptions to planned events- ie:
weddings. It was noted that many book rack need repair prior to the
new refinishing.
It was noted that
many school floor tiles are loose- specifically around 1st
grade rooms. This will be added to the maintenance work list.
It was recommended
that the front church sign get new landscaping.
Grounds updates
– Cleanup Day:
The group discussed
that the grounds need some extra work due to the drought conditions
last summer; many shrubs need to be removed (and not replaced).
They agreed to do this effort separate from the spring cleanup day-
some time in early April- date TBD.
Cleanup Day will
be Saturday April 26th.
Summer Painting:
It was agreed that
we will utilize David Endres as a supervisor of the paint projects
this summer along with summer high school help. The projects are:
old school hallway and door frames. There are also some areas at
church and the rectory that require painting.
Next meeting planned Monday
April 14th 7:30 (No March mtg)
RETURN TO TOP
PROJECTS PRIORITY/COMMENT
|
Repair floor
door stops for double doors in school new wing
|
Compl |
|
|
Install
thermostat covers in school |
Compl |
Maint |
|
Repair school
slate roof- dormer change |
Compl |
|
|
1st
grade paper towel dispenser change. |
Compl |
|
|
|
|
|
|
School
chiller |
Planned
|
Century |
|
Pew
refinishing- center sections |
Planned |
Trinity May
30- June 28 |
|
|
|
|
|
The fresh air
vents around church need to be painted |
painting |
Spring/summer |
|
Replace gutter
on back side of church |
Roof work |
Spring/sum
|
|
Mark reserved
parking spots for musicians/staff- ok 3 by fence |
painting |
Spring/summer |
|
AC units for
room 102 |
Utilities |
Century |
|
Replace key
pads at school |
Doors |
|
|
Repair
exterior school door in new lower level by gym- threshold
sticks |
Doors |
|
|
Church doors-
some need paint & repair, Front door- new urethanes |
painting |
Spring/summer |
|
Chair storage-
plan to purchase more racks or modify existing |
other |
Plan with
undercroft |
|
Repair
threshold at room 19 |
Flooring |
Summer |
|
Repair loose
tile at school |
Flooring |
Summer |
|
Repair old
school copula |
Roof work |
Spring/summer |
|
Clean up
cables on Childs Garden building |
other |
Spring/summer |
|
Repair roof
vent over stage to allow opening with rope |
Roof work |
Maintenance |
|
|
|
|
|
Landscape the
old pond area |
Landscape |
|
|
Landscape
around the front church sign |
Landscape |
|
|
Landscape the
planters in the amphitheater |
Landscape |
|
|
|
|
|
|
Lower boiler
room- controls need to be updated. It was proposed that we
upgrade the controls overall for better facility managing.
|
Utilities |
Planned- V.
Feldman |
|
Black railing
around Church school & rectory painting- every 2-3 years |
painting |
Maint Summer |
Maintain all gutters/ downspouts and window wells
|
Monitor |
Maint- ongoing |
|
Church Sound
System-
Phase 3- other
improvements if needed- replace amp? repl wireless mic? |
Monitor |
|
|
Tree Memorial
plan: Allison, O’Shaunessey requests-proposed donor plaque |
Study |
|
|
Put an awning
by the gym lobby entrance |
Study |
Need design |
|
HVAC
cost/benefit at Childs Garden |
Study
|
|
|
Install a new
fence with gate opening to ease disposing of yard waste |
On Hold |
Quote: $1090 |
|
School desks-
refurbish? |
On Hold |
cost/benefit |
|