|
St.
Antoninus Building & Grounds Commission
Date: Jan. 12,
2009
Attendees:
Tim Hornsby, Mark
Cappel, Greg Langenbrunner, Mike Egner, Mary Hirlinger, Bill
McIntyre, Peggy James
Discussion
Items:
Updates on recent
Maintenance:
New smart boards (2) were installed at school over the
Christmas break.
Sidewalk sections were replaced (thanks! Jeff Muenchen)
Annual Inspections completed: fire alarm, sprinkler system
Jarod’s law update- radon testing to be done next week, stage
back drops were cabled for security.
Changed over to “foamy soap”; new supplier, part of going
“green”
School doors were repaired and new code pads were installed.
Lights changed, gym drinking fountain repaired
Replaced gutter on backside of church near breezeway
Chipmunk problem was address- need to monitor
Rectory chimney cap was fixed (thanks! Langenbrunners)
Other new
discussion from group:
-
School parking
lot drain needs repair around the outer structure- keep safety
cone on for now.
-
Use LDL lights in
emergency lighting
-
Look into a small
dumpster on wheels be moved closer to the back of the undercroft
-
Downspouts were
stolen from a 2 places at Church. Waiting on contractor to
install; replacing with aluminum.
-
With recent
copper theft.. should there be better lighting outside church?
Should the pines be removed?
-
Should cleanup
activity include a 2nd day in the early summer to do
trimming after new growth.
-
More storage is
needed in the gym teacher office; studying the possibility of
removing the old sliding gate to allow room for shelving.
Summer project
maintenance proposal:
Remove wood ramp
from Childs Garden Volunteers
Repair all door
thresh hold/ tile
(front entrance to school, 1st grade room, gym
lobby) Contract and/or Maint.
Paint back side of
gym wall on 2nd floor of school hallway.
Volunteers/ summer help
Paint ramp area
walls
Volunteers/ summer help
Café
wall
Volunteers/ summer help
Paint gym lobby
columns
Maintenance
Paint outside
doors/ around church
Contract
Paint parking lot
light poles
Contract and/or Maint.
Repair parking lot
light
Maintenance
Repair rectory
patio gate
Maintenance
Repair blacktop
cracks
Jacobson
Repair carpet by
baptismal font/ add timer to font
Contractor/ Maint
Possible Capital
projects:
Security cameras
School PA system
Windows in brides
room, greeting room & sacristy
Next meeting planned Monday
February 9th 7:30
Topics:
School
Summer Plans; Spring Cleanup Date- April 25th
RETURN TO TOP
St.
Antoninus Building & Grounds Commission
Date: Sept, 2008
There was no
September Meeting
Below are the notes
from the August meeting and various topics that have come up since.
The past 2 months
have been very busy with school startup activities, completing the
undercroft and the wind storm. The storm did take down a number of
branches and trees around the facility and caused some minor damage
on our school slate roof. The majority of the cleanup is complete;
there are a couple tree stumps that need to be removed.
Thanks! to Greg
Lester and Tim Hornsby for their leadership and planning for “Clean
up Day” for Back on Saturday August 16th. Also Thanks to
the many volunteers who spent time around the grounds that week.
Thanks! to Norb,
Steve and Jim for their leadership and countless hours in the
undercroft.
Thanks to our
maintenance men, Jim & Harry for an excellent response to the
facility after the wind storm.
Thanks! to the 14
Elder students who volunteered their time on Oct. 6th.
They cleaned the parking lot and grounds after the wind storm, and
did other service work around the facility.
Discussion Items
– also see attached project list
Improve the
cleaning of the church stairwells and undercroft restrooms; consider
professional services
Look into a
memorial garden- Norb Guetle volunteered to get small committee
together.
Remove the Child’s
Garden handicap ramp.
Look into a “go
green” initiative
Finish Punch List
items from undercroft.
Fix the chipmunk
problem around facility
Fill dirt in needed
in some areas to get proper drainage away from the building.
Lights in church
need to be replaced
Jarod’s law -
secure all tables that are stored upright; specifically ones on gym
stage.
Undercroft
notes:
There is a new
policy for parishioner’s private party use of the undercroft.
Important changes include a required/refundable security deposit and
decorating limitations (nothing is allowed hung from the ceilings or
taped to the walls; also no open flames are allowed). School
functions will also need to comply with these decorating
requirements.
Groups having
meetings in the undercroft must schedule through Beth at the
rectory. The Youth room is being setup as the common meeting room.
Groups should never setup or rearrange the undercroft space without
permission from the parish office. Doing so, causes additional work
for our maintenance men and may disrupt a setup being done for
another planned event.
Next meeting planned Monday
Oct. 13th 7:30 in Undercroft
RETURN TO TOP
PROJECTS PRIORITY/COMMENT
|
Replace key pads at school |
High |
Complete |
|
The fresh air vents around church need to be
painted |
High |
|
|
Replace gutter on back side of church & possibly
rectory gutter repair |
High |
|
|
Mark reserved parking spots for musicians/staff-
ok 3 by fence |
High |
|
|
AC units for room 102 |
High |
|
|
Repair loose
tile at school |
Med |
|
|
Repair old school copula + new wind damage |
Med |
|
|
Clean up cables
on Childs Garden building |
Med |
|
|
Landscape the
old pond area |
Med |
|
|
Landscape around the front church sign |
Med |
|
|
Repair roof vent over stage to allow opening with
rope |
Med |
Maintenance |
|
Tree Memorial plan: Allison, O’Shaunessey
requests-proposed donor plaque |
Med |
|
|
Landscaping plan for the planters in the
amphitheater |
Med |
|
|
Put an awning by the gym lobby entrance
|
Med |
Need design |
|
Lower boiler
room- controls need to be updated. It was proposed that we
upgrade the controls overall for better facility managing.
|
Med |
|
|
Black railing around Church school & rectory
painting- every 2-3 years |
Med |
Maint Summer |
|
Wash statue |
New |
|
|
Check around facility for additional painting
needs- especially doors. |
New |
|
|
Modify baptismal water flow; then fix floor
around baptismal font. |
New |
|
|
Consider getting UV coverage on the skylights at
church |
New |
|
|
Replace windows in greeting room and sacristy |
New |
|
|
Develop overall/ long term school air conditional
needs plan |
New |
|
|
Study HVAC
cost/benefit at Childs Garden |
Monitor |
|
|
Church Sound System-
Phase 3- other improvements if needed- replace
amp? repl wireless mic? |
Monitor |
Peg Delaney is studying system |
Maintain all gutters/ downspouts and window wells
|
Monitor |
Maint- ongoing |
|
Install a new fence with gate opening to ease
disposing of yard waste |
On Hold |
Quote: $1090 |
|
School desks- refurbish? |
On Hold |
cost/benefit |
|